Easy2Siksha.com
We calculate the earliest time each event can occur:
• Event 1 = 0
• Event 2 = 0 + 2 = 2
• Event 3 = 2 + 4 = 6
• Event 7 = 2 + 3 = 5
• Event 4 = 6 + 3 = 9
• Event 5 = 6 + 0 = 6
• Event 6 = max(9+0, 6+6) = max(9,12) = 12
• Event 8 = 5 + 8 = 13
• Event 9 = max(12+7, 13+2) = max(19,15) = 19
So earliest event times: E1=0, E2=2, E3=6, E4=9, E5=6, E6=12, E7=5, E8=13, E9=19.
Step 4: Backward Pass (Latest Event Times)
Start from the end (Event 9 = 19):
• Event 9 = 19
• Event 6 = 19 - 7 = 12
• Event 8 = 19 - 2 = 17 (but earliest was 13, so slack exists)
• Event 4 = 12 - 0 = 12
• Event 5 = 12 - 6 = 6
• Event 3 = min(12-3, 6-0) = min(9,6) = 6
• Event 7 = 17 - 8 = 9
• Event 2 = min(6-4, 9-3) = min(2,6) = 2
• Event 1 = 2 - 2 = 0
So latest event times: L1=0, L2=2, L3=6, L4=12, L5=6, L6=12, L7=9, L8=17, L9=19.
Step 5: Critical Path
Critical path = path with zero slack (earliest = latest). Check paths:
• Path 1→2→3→5→6→9 = 2+4+0+6+7 = 19
• Path 1→2→3→4→6→9 = 2+4+3+0+7 = 16
• Path 1→2→7→8→9 = 2+3+8+2 = 15
So the critical path is 1→2→3→5→6→9, with project duration = 19.
Step 6: Floats
Float = Latest Start – Earliest Start (or Latest Finish – Earliest Finish).
• Activities on critical path (1→2, 2→3, 3→5, 5→6, 6→9) have zero float.
• Others (like 2→7, 3→4, 4→6, 7→8, 8→9) have positive float.